YEARLY GENERATION REPORT

2026
Sl No.StationInstalled
Capacity (MW)
Annual Target
(MU)
Actual Generation
(KWH)
Actual
(MU)
Achievement
(%)
Load Max
(KW)
Load Min
(KW)
Grid Unavailability of Grid/PSS
(Hrs/Min)
Avg Discharge
(Cusec)
1Kataiya19.2014.00000000.0000000.00000 / 353372
2Valmikinagar15.0025.00000054525905.45259021.81490012008 / 4253640.21
3Triveni3.003.00000018064901.80649060.221800018 / 5351013.9
4Dehri6.608.00000014845901.48459018.56140050065 / 5811611.28
5Barun3.309.0000003668500.3668504.081300010 / 1031017.07
6Agnoor1.002.00000000.0000000.00000 / 00
7Dhelabagh1.003.000000975000.0975003.253000163 / 794360
8Nasriganj1.003.00000030000.0030000.103001407 / 441051
9Sebari1.003.00000000.0000000.00000 / 00
10Jainagra1.002.00000000.0000000.00000 / 00
11Shrikhinda0.702.0000001540600.1540607.703000203 / 1234308.69
12Belsar1.002.00000000.0000000.00000 / 00
13Arwal0.501.000000228000.0228002.2828011523 / 291281.43
TOTAL54.3077.00000093878809.38788012.19105801955497 / 404212655.59

Note:- E.S.F.= Electric Supply Fail, F.C.= Force closed    L.D.= Low Discharge, L.V.= Low Voltage    T.R. Jam = Trash Rack Jam